TransportationWednesday, November 18
RTD has launched planning for a 5.5-mile N Line extension in Adams County
The AM Denver team
If you ride the N Line, or want to, the next step is here. RTD launched the project development phase Monday for an extension that would add about 5.5 miles of commuter rail north of the Eastlake·124th station. Proposed stations sit near York Street and 144th Avenue and near Highway 7 and 162nd Avenue. The work is backed by $12 million the RTD board approved in July.
Nothing's being built yet. Denverite reports the design phase will take at least a year, and then RTD has to find construction money. CBS News says completing the extension depends on securing state and federal construction funding.
The N Line extension has been decades in the making
- 2004The N Line is conceived as part of the FasTracks system.
- 2014Construction begins on the N Line.
- 2020RTD's most recent rail network expansion takes place.
- July 2026The RTD board approves up to $12 million for project development.
- Nov. 16RTD launches the project development phase.
Sources: Westminster Window, Denverite
- Design phase: at least a year
- Early funding: FasTracks Internal Savings Account
- Full N Line: 18.5 miles, Union Station to north Thornton
- Last RTD rail expansion: 2020
Sources: Westminster Window, Denver7, Denverite, CBS News