TransitTop story
RTD sets aside up to $12 million to plan the final 5.5 miles of the N Line
The N Line extension starts with planning money, not construction money
- $12 million
- set aside for planning, environmental review and engineering
- 5.5 miles
- of N Line extension north of Eastlake•124th
- $55 million
- estimated for all pre-construction work
- 1.2 million+
- N Line riders in 2025, RTD says
Sources: Denver7, Denver Gazette
If you ride the N Line or live up north, the unfinished stretch is moving again. RTD has launched a project-development phase for the last 5.5 miles north of the Eastlake•124th station to Highway 7, and it will put up to $12 million toward environmental review, corridor validation and preliminary engineering, according to a news release. The money follows board approval of a partnership with Adams County.
Riders are part of the pitch. The line had about 760,000 in 2021, its first full year, and Denver7 reports ridership keeps climbing. Plans call for stations near York Street and 144th Avenue and near State Highway 7 and 162nd Avenue. Project manager Nabil Haddad says many more details are coming in August 2027.
Construction on the N Line extension is likely no earlier than 2029
- 2004Metro voters approve the FasTracks program.
- Sept. 2020The first 13 miles of the N Line open.
- Aug. 2027RTD's project manager says many more details will be ready.
- 2029Construction is likely to begin, and no earlier than this year.
- 2034RTD must show how unfinished FasTracks segments can be completed, under a 2024 state mandate.
Sources: Denver7, Denver Gazette
- Remaining capital cost: $395.7 million in 2024 dollars
- Construction funding: not yet identified
- Existing line: roughly 3,600 average weekday riders
- Extension forecast: 1,500 daily boardings by 2045